Veritas Report — Project Atlas — CO-03

Commercial office — Austin, TX · Contract $1,200,000 · CO claimed $87,000 · Reviewed 2026-03-14

Claimed
$87,000
Contractor total
Veritas justifiable range
$62,000–$66,000
Supported by contract + docs
Difference
-$21k to -$25k
Unsupported / duplicate

Executive summary

Three items require challenge. Two are unsupported by the contract: one exceeds the 10% markup cap (prices at 18%), one duplicates scope already compensated under General Requirements §1.8. One material item lacks backup. Structural steel is supported.

Line itemClaimedVeritasStatus
Structural steel — labor + material$42,000$42,000Approved
Miscellaneous coordination$12,400$0Already in scope §1.8
Overtime — as required$18,500$9,800 (at 10% cap)18% > 10% cap §4.2
Consumables & rentals$14,100$7,200 pendingNo quote attached

Markup detail (§4.2)

Contract caps combined overhead & profit at 10% on change-order work. Contractor applied 18% on labor. Veritas recomputes: 10% allowable = $1,640 over base. Excess = $8,700. Recommendation: cap at contract rate.

Missing documentation

Consumables invoice not provided. Without unit pricing or vendor quote, amount cannot be verified. Request: vendor quote + delivery tickets before approval.

Recommended response — ready to send

“Per §4.2 markup is capped at 10%. Item 2 prices at 18% ($8,700 over cap) and Item 3 duplicates scope under §1.8 ($12,400). We propose $64,000 as the justifiable total, pending backup for Item 4. Please provide unit pricing and the omitted quote for reconsideration. — Prepared for Project Atlas, CO-03”